Project Planning and Controlling The Construction Project of A Hospital Hemodialysis Unit Located In Tangerang Using The Crashing Method
DOI:
https://doi.org/10.46799/ajesh.v2i8.100Keywords:
Project, Planning, Controlling, Crashing, DurationAbstract
The research was carried out by project planning and controlling to analyze the time duration and cost of adding labor and overtime hours at work on amendments to the construction of a hospital Hemodialysis unit located in Tangerang with the accelerated crashing method. Research analysis to see project planning and project control of amendments to the work of building a Hemodialysis unit for Crashing analysis work carried out by the accelerated method of adding working hours, adding labor and the combination of time duration to find the most optimal value.
Downloads
Downloads
Published
Issue
Section
License
Copyright (c) 2023 Dwi Dinariana, Fitri Suryani , Ryan Nurachman

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International. that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.