Time Control Analysis on The Warehousing Construction Package and Supporting Facilities of Juwata Airport Using The Earned Value Method

Authors

  • Ridha Annisa Imaniar Master of Civil Engineering Study Program, Faculty of Engineering, University of August 17, 1945 Surabaya, Indonesia
  • Budi Witjaksana Master of Civil Engineering Study Program, Faculty of Engineering, University of August 17, 1945 Surabaya, Indonesia
  • Jaka Purnama Master of Civil Engineering Study Program, Faculty of Engineering, University of August 17, 1945 Surabaya, Indonesia

DOI:

https://doi.org/10.46799/ajesh.v4i6.635

Keywords:

Earned Value, Cost and Time Performance, Job Acceleration

Abstract

The construction of warehouses and supporting facilities at Juwata Airport there are several obstacles that cause delays in the implementation of work, so a method of work control is needed, namely the earned value method by assessing the cost performance and time of project implementation such as Cost Variance (CV), Schedule Variance (SV), Schedule Performance Index (SPI), and Cost Performance Index Index (CPI) as well as estimated cost and project completion time. Using the earned value method, a CV value of < 0 was obtained in weeks 20 to 26, which describes a greater cost than planned, while in weeks 24 to 26, SV value < 0 is obtained, which describes delays. And for the CPI value of > 0 in weeks 20 to 26, this describes the costs incurred as smaller than planned, while in weeks 24 to 26 the SPI value < 1 which describes delays. The estimated final cost of the project obtained from EAC was Rp. 15,019,062,678.43 and the estimated time / Time Estimate (TE) in the 26th week showed the figure of 239 calendar days so that the completion time was 28 days late from the contract schedule. And the solution for the delay is to accelerate the work with an additional cost of Rp. 68,970,000

Downloads

Download data is not yet available.

Downloads

Published

2025-06-27